Week ending December 24, 2005
Landfill Gas System- Drilling of the gas wells continued all week.
Twelve wells have been installed.
Air Monitoring- Five perimeter H2S air monitoring units were received
and will be installed next week. High range units for H2S source
monitoring are back ordered.
Contact water management - APAC-Reno's consultant met with Johnson
County Wastewater staff and Johnson County Environmental staff to
discuss status of review for discharge of the contact water through the
county's wastewater treatment system. After discussing, it was decided
the application stood little chance for approval at this time, primarily
due to the existing hydraulic load on the wastewater plant. The plant is
undergoing modifications but will not increase capacity until
October/November, 2006.
Hydrogeologic Investigation- Sampling completed on newly installed
perimeter wells and landfill wells on Monday. Another ground water well
will be installed near the lower pond on 12/28/05. Goal is to have
report to KDHE by mid January, 2006.
Intermediate cover- Due to cold earlier in the week and wet
conditions, no intermediate cover was placed.
|