APAC-Reno installed the final gas well as part of the landfill gas
collection system. The pipeline system to connect the gas wells is
expected to take 2-3 weeks to construct.
APAC-Reno continues to treat the contact water collected in the lower
east pond with hydrogen peroxide and caustic. The west and south seeps
continue flowing at 15 gallons per minute each. A meeting is scheduled
early next week with the KDHE-Bureau of Water to discuss revisions to
the landfill NPDES permit. With a revised National Pollutant Discharge
Elimination System (NPDES) permit, APAC-Reno will try and increase flow
from the west and south seeps to speed up the dewatering process.
The perimeter air monitoring H2S meters are operating and the data is
being collected and downloaded by JCED. The H2S monitors to be placed
inside the landfill have been received and are undergoing trial runs
with the telemetry system to insure the alarm system works. They should
be set next week. No reported problems with perimeter monitors have
occurred to date.
The intermediate cover construction continued through Thursday and
should be completed early next week covering over the southern landfill
areas.
The Hydrogeologic Investigation Site Report was submitted to the
Kansas Department of Health and Environment on Wednesday, 1/18/06.