July 2008
- No hydrogen sulfide readings were detected by any of the monitors.
- An estimated 2,008,800 cubic feet of landfill gas removed and treated in July
- An estimated gallons of contact water (water
that has seeped through the landfill and accumulated underneath the
landfill) and well water were removed and treated in July.
- Six gas probes were installed along the east boundary. No methane or hydrogen sulfide gases were detected.
August 2008
- One hydrogen sulfide
reading of 0.02 part per million was detected at 4:06 pm on August 5,
2008.
- An estimated 1,944,000 cubic feet of landfill gas removed and treated in August.
- An estimated 3,500,879
gallons of contact water (water that has seeped through the landfill and
accumulated underneath the landfill) and well water were removed and
treated in August.
September 2008
- No hydrogen sulfide detections by any of the air monitors.
- An estimated 1,944,000 cubic feet of landfill gas removed and treated in September.
- An estimated 2,228,312 gallons of contact water (water that has seeped through the landfill
and accumulated underneath the landfill) and well water were removed and treated in September.
October 2008
-
No hydrogen sulfide detections by any of the air monitors.
-
An estimated 2,008,800 cubic feet of landfill gas removed and
treated in October.
-
An estimated 3,103,084 gallons of contact water (water that has seeped through the landfill
and accumulated underneath the landfill) and well water were removed
and treated in October.
- On October 30th, the north perimeter monitor had a
reading of 0.01 ppm H2S at 7:10 am and the southeast monitor had
several readings of 0.01 ppm H2S between 1:45 am and 3:15 am.
-
Methane monitoring on-site and along Metcalf Ave continues with no
detectable measurements.
November 2008
-
In November hydrogen sulfide (H2S) was detected on seven days. The
north, northeast and southeast perimeter monitors detected H2S at a
concentration of 0.01ppm and one instance of 0.02ppm. Up until
November 19 the 10,000 gallon well water storage tank was plumbed
directly to the lower pond with hydrogen peroxide added at the well
head. It is believed that given the increase in H2S in the
landfill that retention time had become insufficient thus
contributing to the H2S readings at the air monitors. The storage
tank discharge was connected to the smaller mixing tanks thus
increasing retention time on November 19. No H2S has been detected
since that time.
-
An estimated 1,944,000 cubic feet of landfill gas removed and treated in November.
-
An estimated 2,550,315 gallons of contact water (water that
has seeped through the landfill and accumulated underneath the
landfill) and well water were removed and treated in November.
-
Methane gas was detected in a gas monitoring well near the southeast
border of the property. The gas collection system was rebalanced to
pull more gas from the perimeter wells. Since the rebalancing,
methane has not been detected in the gas monitoring well. However,
there has been an increase in the methane and H2S concentration of
the landfill gas at the blower. These levels are acceptable under
the existing air permit. APAC is modifying the gas collection
system to burn more landfill gas. This modification will be
submitted to the Kansas Department of Health and Environment in
December for approval.
December 2008
-
No hydrogen sulfide detected at air monitors.
-
An estimated 2,008,800 cubic feet of landfill gas removed and treated in December.
- An estimated 1,574,634 gallons of contact water (water that has seeped
through the landfill and accumulated underneath the landfill) and well
water were removed and treated in December.
|